Relocate the existing dual Grundfos vertical multistage pump system during demolition and reinstall under new grandstand including addition of a 3rd duty pump and controls for increased flow and reliability.
Rebuild the pump manifold in buttwelded PE to facilitate future upgrades and modification and incorporate new control valves and sensory equipment.
Temporarily install the existing 104 solenoid valve manifold to facilitate grandstand construction whilst maintaining full control of irrigation.
Final relocation and rebuild of the manifold to new plantroom with custom copper pipe works and support bracketry.
Installation and commissioning of fertigation dosing systems.
Reinstall the custom toggle controller and rewire all valves.
Commissioning and handover to the SCG trust
Works were staged and night shift undertaken to ensure there was no disruption to the critical irrigation requirements and game schedules.